Caltrans District 7 HQ Building Replacement (Design/Build)
Los Angeles, CA
Hot Topics
Feb-2004
HIGHLIGHTS AND ACHIEVEMENTS
Project Design:
M&F is working to respond to the last
few comments regarding interiors and vibration isolation. M&F is also
resolving the design solution to the "skateboard" sloped plaza slab
over the Main Street parking garage entry.
Construction:
Scrim panel installation on the east and
west facades is 90% complete and installation of the associated pneumatic
tubing on the building exterior has been completed. Installation of the scrim
operator pistons is underway and an operating scrim panel mockup has been
activated on the east elevation.
Installation of the support steel for the
precast concrete panels on the plaza has been completed. Precast panels are
to be delivered to the site in early March.
Model Glass has completed the strip windows
installation on all elevations. Fill in of waterproofing and glazing continued
at the former manlift location.
Installation of elevators cabs, wiring
and entrances continued. The service and ADA cabs continue to operate smoothly.
Interior work is progressing on all levels,
the 5th floor being the most complete, followed by the 2nd floor. Floors continue
to be finished from bottom to top.
The project team reviewed and accepted with
comments the tile installation in the 5th floor mockup.
Annotated Design Guidelines and Project
Specifications - Change Order #27 was signed by the State and M&F, concluding
the preparation and acceptance of the annotated design guidelines and performance
criteria.
Modular Furniture: Fabrication drawings
for all floors continued to be developed by the Keller Group and are being reviewed
by DGS and Caltrans as they are completed. Electronic files of floors 1 through
8 have been transmitted to M&F to locate floor penetrations for installation
of voice/data and power distribution.
Land Exchange: Recording of the grant
deed for exchange of the 1st Street Properties from the City of Los Angeles
to the State occurred on February 6, 2004, thus completing the first phase of
the land exchange which will be concluded in 2005 with the State's transfer
of the existing Caltrans District 7 HQ site, after demolition is completed.
Irrevocable Permit (Permanent Encroachment
Easement): Documents have been submitted and are being reviewed by the City
of Los Angeles' Department of Public Works, which is to respond by the end of
April 2004.
Public Art Program: Meetings between
all subcontractors and design team members involved with the Keith Sonnier art
piece were held at which the installation schedule was reviewed and potential
sub-trade coordination issues were discussed. Work continued to install the
vertical art piece angles for Keith Sonnier's piece. The public art pieces by
Alan Rath and Renee Green continue to be in their shop drawing phases. The rough-ins
for the "Fiver" art piece are to be installed in place mid-March.
Marc Pally continues to help coordinate with M&F and the artists in processing
payment and art piece coordination issues. Marc Pally and the M&F representatives
will be present at the early April owner's meeting to update the State on the
progress of the art in the building.
Project Budget: A total of $3,441,550
in change orders has been executed, with $1,225,731 in open PCO's remaining
through February 2004, resulting in an available project contingency of $1,245,007.
Three change orders were executed this month for a total increase to the M&F's
contract of $3,355. Also, URS contract was increased by $116,900 for continued
work of a Site Manager. See the Financial Report in the Appendix for further
details.
11th Floor Tenant: RESD continues to
search for State tenant's to occupy the space.
Retail Space - California Bear Credit
Union has elected to employ their own design/build contractor who is currently
preparing a space plan that will be forwarded to the State by mid March to include
in the Lease documents.
Public Utility Incentive Funding: Though
The Gas Company's commitment for $356,805 has been received; the similar commitment
from LADWP has not and remains a critical issue. The project team is working
on a project advancement report due to The Gas Company on April 4th. A meeting
is scheduled for early March with LADWP to discuss their energy savings incentive
program focused on HVAC chiller design. Finally, M&F (Ove Arup) is following
up with The Gas Company regarding status of the Savings in Design Program.
SBE/DVBE: Currently, M&F has attained
50% of the overall Small Business Enterprise goal and 63% of the overall Disabled
Veteran Business Enterprise goals for the project. In addition, URS contracted
level remains at approximately 66% of the 3% DVBE requirement contained in its
contract through the use of a DVBE cost estimator.
Move Coordination - Caltrans
CRITICAL ISSUES
LADOT Lease: As of the end of February,
the lease document has not been agreed upon and negotiations between the legal
staffs of the City of LA and the State are continuing. The project team successfully
worked with the City to agree on the project scope revisions necessary to reduce
the tenant improvement budget to $5M. Construction of the LADOT space on floors
9 and 10 continues.
Traffic Management Center (TMC) - The
TMC remains behind schedule. A recovery schedule based on a six day work week
may result in the project's completion by mid September, but more likely mid
October 2004. With the six-month switch over schedule required by CT7, the existing
TMC will not be fully vacated until April 2005, thus delaying the start of demolition
of the existing headquarters building.
Public Utility Incentive Funding: Although
a commitment letter was received when the economics were prepared and approved,
the final commitment to fund $455,000 has still not been obtained.
LEED Certification - The latest update
of M&F's LEED consultant's credit summary indicates that two credits, previously
thought to be safe, are now questionable, leaving the project with only 31 credits,
which are two credits short of a Silver Certification. The project team is studying
all credits potentials and will resolve the two now in question. Please see
the Project Status section for more detail.