Caltrans District 7 HQ Building Replacement (Design/Build)
Los Angeles, CA


  Schedule Activities

PROJECT SCHEDULE

The M&F Project Schedule (refer to Appendix Item 3.2) has been updated to reflect the current

project plan as of February 29, 2004. The current milestone schedule is:

 
Events
Start Dates
Finish Dates
Contracted
Current Schedule
Contracted
Current Schedule


Phase 1 - Notice to Proceed (Design & Construction Of New Headquarters Replacement Building)
February 4, 2002
February 4, 2002
N/A
N/A
First Street Properties Available
May 1, 2002
May 1, 2002
N/A
N/A
Building Commissioning Start
January 8, 2004
January 8, 2004
N/A
N/A
Certificate of Compliance (Core & Shell)/All Parking Complete
N/A
N/A
June 25, 2004
June 27, 2004
First (Zone 1) Certificate of Occupancy (10% to 20% Beneficial Occupancy)
N/A
N/A
July 27, 2004
August 13, 2004
Second (Zone 2) Certificate of Occupancy (30% to 40% Beneficial Occupancy)
N/A
N/A
August 26, 2004
August 26, 2004
Third (Zone 3) Certificate of Occupancy (40% to 50% Beneficial Occupancy)
N/A
N/A
September 20, 2004
September 20, 2004
LADOT Certificate of Occupancy
N/A
N/A
October 26, 2004
October 26, 2004
Phase 1 Complete (Receipt of Last Certificate of Occupancy, completion of Punch list, and receipt of Phase 1 Certificate of Final Completion.)
N/A
N/A
October 26, 2004
October 26, 2004
Phase 2 - Notice To Proceed (Tenant Occupancy Begins)
July 27, 2004
July 27, 2004
N/A
N/A
Phase 2 - Complete (Commissioning Complete, Receipt of Phase 2 Certificate of Final Completion.)
N/A
N/A
December 31, 2004
December 31, 2004
Phase 3 - Notice To Proceed (Demolition of Existing Caltrans Headquarters/Post Occupancy Evaluation Phase Begins)
January 3, 2005
January 3, 2005
N/A
N/A
Phase 3 Complete (Demolition Complete, Post Occupancy Evaluation Phase Complete, Receipt of Phase 3 Certificate of Final Completion)
N/A
N/A
July 1, 2005
July 1, 2005

The project remains on schedule to provide complete occupancy by the end of 2004.